Site Acceptance Test for Custom Lantern Displays
A site acceptance test, or SAT, is the documented check that an installed custom lantern system works at its destination under the agreed site conditions. It should verify delivered configuration, physical installation, power and controls, nighttime appearance, public-interface controls, maintainability, training, and handover evidence. A signed SAT record should state what passed, what remains open, who owns each action, and whether public operation is authorized.
SAT is not a repeat factory tour and it is not a substitute for permits, local electrical or structural review, venue safety procedures, or competent professional judgment. Its value is to connect the approved project basis to the actual route before the display enters service.
![]()
What is a site acceptance test?
A site acceptance test evaluates installed equipment or systems in their operating environment. IEC 62381:2024 covers factory acceptance, site acceptance, and site integration testing for automation systems and explains that test plans should be adapted to the specific plant, equipment, and requirements. The lantern-project protocol should likewise be project-specific: it needs the released drawings, destination conditions, contract boundaries, applicable codes, authority requirements, and venue operating plan.
The closest general sequence is simple: confirm prerequisites, inspect the installed configuration, energize under controlled conditions, test functions and interfaces, record results, close exceptions, and transfer the approved package to operations. The detailed criteria differ for a small static display, a long outdoor trail, a moving feature, or an interactive installation.
Separate FAT, SAT, commissioning, and public opening
| Control point | Primary question | What it cannot prove alone |
|---|---|---|
| Factory acceptance test | Did the staged package meet the agreed pre-shipment requirements? | Destination anchors, final cable routes, site integration, weather exposure, local approval, and public operation. |
| Installation inspection | Was the delivered package assembled in the right location and configuration? | Full functional performance and trained operating response. |
| Commissioning | Were components, circuits, controls, interfaces, and operating sequences checked and brought into service? | Formal buyer acceptance unless the contract makes commissioning records part of acceptance. |
| Site acceptance test | Does the installed project meet the agreed destination acceptance criteria? | Conditions outside the stated test basis or future public-operation performance. |
| Opening authorization | Have the venue and relevant responsible parties approved the attraction for the intended operating state? | Ongoing inspections, weather decisions, maintenance, and incident response. |
The earlier factory acceptance test guide defines the pre-shipment boundary. SAT should import its module IDs, approved exceptions, test evidence, and packing-release record rather than starting with an untraceable folder of photographs.
Freeze the site acceptance basis before energization
Do not write the SAT checklist after installation is already complete. Issue the test basis before mobilization and identify the current revision of the display schedule, layout, assembly drawings, foundation or anchoring information, electrical design, control narrative, finish references, operating plan, and handover deliverables. Mark assumptions and unresolved interfaces explicitly.
The responsible site team should also confirm that access is controlled, installation work is complete enough for the planned test, temporary works are stable, competent people are assigned, required inspections are available, and weather conditions allow the test. In the United States, applicable requirements depend on the work and jurisdiction. OSHA’s wiring design and protection rule includes grounding and inspection provisions, while its temporary wiring rule addresses matters such as physical cable protection and weatherproof enclosures. The project electrical professional and local authority must determine what applies.
Use a twelve-field SAT record
| Field | What to record | Why it matters |
|---|---|---|
| Zone and item ID | Display, module, circuit, controller, drawing, and location reference. | Prevents a result from being applied to the wrong unit. |
| Requirement source | Contract clause, approved drawing, schedule, sample, code, or test procedure. | Keeps acceptance tied to an agreed basis. |
| Prerequisite | Installation completion, safe access, inspection, instrument, weather, or energization condition. | Shows whether the test result is valid. |
| Acceptance criterion | Observable pass condition and tolerance where appropriate. | Replaces subjective comments with a decision rule. |
| Method | Visual review, measurement, functional test, scene test, document review, or demonstration. | Makes the result repeatable. |
| Actual result | Observation, reading, file reference, photograph, or test record. | Preserves evidence, not only a tick mark. |
| Responsible and witness parties | Who performed, observed, reviewed, and accepted. | Clarifies authority and accountability. |
| Exception | Location, condition, affected requirement, and operational consequence. | Defines the real scope of the issue. |
| Disposition | Accept, conditional accept, retest, hold, or remove from service. | States what may happen next. |
| Owner and due point | Named role plus date, milestone, or opening condition. | Prevents open work from disappearing. |
| Closure evidence | Repair record, repeat result, photograph, or signed review. | Proves that the exception was resolved. |
| Operating release | Authorized state, excluded areas, restrictions, and approver. | Separates testing from permission to open. |
Run the site acceptance test in a controlled sequence
1. Reconcile delivery and configuration
Match the delivered modules, spare parts, tools, controllers, cables, repair materials, documents, and revisions to the released packing and installation records. Trace any transport or storage damage to a specific item. Confirm that factory exceptions marked closed have closure evidence and that approved open items were transferred into the site register.
2. Inspect structure, position, and access
Check the installed location, orientation, module joints, bases, anchors or connections, clearances, barriers, sharp-edge controls, access panels, drainage intent, maintenance reach, and protected service routes. Structural adequacy must be reviewed against the project design basis and actual support conditions by the responsible qualified parties; a visual SAT alone cannot certify it.
3. Inspect power and electrical protection
Verify the supply and distribution arrangement, identification, enclosure condition, grounding or bonding provisions, cable protection, connectors, protective devices, isolation points, load allocation, and wet-location measures against the approved design. Record tests and instruments where the procedure requires them. The event power distribution guide helps organize the route-level power plan before these acceptance checks.
4. Test controls and operating scenes
Demonstrate each approved scene, timer, dimming level, sequence, control group, restart behavior, local override, and fault response that is within scope. Test the system in the configuration operations will actually use. If a network, show-control, audio, or venue system is not ready, record the interface as untested instead of treating a standalone demonstration as full integration.
5. Review nighttime appearance from visitor positions
Walk the intended approach, threshold, viewing nodes, route transitions, rest areas, and exit. Look for dark modules, exposed glare, inconsistent color, visible seams, unintended reflections, obstructed sightlines, distracting service equipment, and scenes that do not read at the agreed viewing distance. Appearance criteria should refer to approved references and locations, not personal preference alone.
6. Test the public interface
Confirm that routes, edges, barriers, interactive points, emergency access, staff sightlines, and queuing assumptions match the venue plan. The U.S. Access Board’s guide to accessible routes explains that accessible routes should connect accessible spaces and generally coincide with circulation paths. Local accessibility obligations and the actual temporary-event layout still need project review.
7. Demonstrate maintenance and recovery
Have the responsible team show safe isolation, access to service points, replacement of agreed consumables or components, controller recovery, daily inspection, weather shutdown, defect logging, and spare-part custody. A system that performs once but cannot be maintained during the run is not ready for reliable operation.
8. Complete training and handover
Transfer current drawings, settings, manuals, inspection records, spares, keys, contact paths, escalation rules, warranty information, open issues, and approved operating restrictions. Record who received training and which tasks require specialist support. The handover pack should let the venue identify the installed configuration and respond without relying on verbal memory.
What is the difference between FAT and SAT?
FAT is performed at the manufacturer’s facility before shipment and verifies the defined pre-shipment scope. SAT is performed after destination installation and verifies real site interfaces, delivered condition, integrated operation, route conditions, and handover. The two tests should share IDs and requirements, but a pass at one stage does not automatically pass the other.
What is the difference between SAT and commissioning?
Commissioning is the broader process of checking, bringing into service, documenting, and handing over systems. SAT is a formal acceptance decision within the project contract or quality plan. Commissioning evidence may support SAT, and the activities may occur together, but the documents should state which action proves function and which action grants acceptance.
What does an acceptance test example look like?
For a programmable lantern gateway, one SAT line could require the installed gateway to match the approved module arrangement, remain clear of the defined route envelope, energize without a recorded fault, run each approved scene, restart into the agreed state, and allow safe access to the service point. The record would cite the drawing and control narrative, identify the witness, attach the result, and open a numbered exception for any failure.
Turn the punch list into an opening decision
A punch list is useful only when every item has a consequence and disposition. Separate cosmetic observations from functional, safety, route, document, and operating-control issues. State whether the affected zone may be energized, tested further, opened with a restriction, or held out of service. Do not let an overall signature erase unresolved lines.
If defects are found, connect them to the agreed change and correction process rather than editing the acceptance basis after the fact. The change order template is appropriate when scope, cost, schedule, or responsibility changes; ordinary nonconformance correction should remain traceable to the existing requirement.
Connect SAT to ongoing operation
Acceptance captures a controlled moment. The venue still needs daily opening checks, weather decisions, preventive maintenance, spare-part control, issue escalation, closing checks, and end-of-run decommissioning. Keep SAT records accessible to operations so recurring faults can be tied to the affected item, setting, repair, and warranty path.