Factory Acceptance Test for Custom Lantern Displays

A factory acceptance test, or FAT, is the controlled pre-shipment review of a custom lantern package against its approved requirements. For a large modular display, it should show that the agreed zones can be assembled, illuminated, controlled, identified, documented, corrected, and released for packing. It is more useful than an informal factory tour because it connects each observation to an acceptance criterion and disposition.

The FAT does not prove that the destination site is ready or that the final installation will pass local review. It reduces avoidable delivery risk while the people, tools, replacement materials, and production records are still close to the work.

Project team inspecting an illuminated dragon and floral lantern display during factory acceptance testing

What is a factory acceptance test?

A factory acceptance test verifies equipment or a custom assembly at the manufacturer’s facility before shipment. TUV Rheinland’s FAT service overview describes checks against contractual requirements, functional testing or simulation, final inspection, and review of documentation and drawings. Those principles translate well to custom festival lanterns, but the exact test plan must follow the contract, approved design, intended site, and applicable local requirements.

For lantern projects, the witness scope can include a complete feature, a representative zone, or defined samples plus records for repeated units. The parties should decide that scope before fabrication reaches the packing stage. If the full route cannot be staged simultaneously, record which interfaces are physically demonstrated, which are checked by measurement, and which remain for site acceptance.

Define FAT, pre-shipment inspection, and site acceptance separately

Control pointMain questionTypical evidence
In-process inspectionAre materials and fabrication following the released information?Material records, dimensions, frame and finish observations, production photos, corrective records.
Factory acceptance testDoes the staged package meet the agreed pre-shipment acceptance criteria?Approved test plan, witnessed results, scene tests, interface checks, punch list, disposition, release record.
Pre-shipment inspectionIs the released work complete, correctly identified, protected, packed, and documented?Packing list, module IDs, package condition, photos, quantities, documents, loading plan.
Site acceptance testDoes the installed system work safely and as intended at the destination?Installed inspections, local electrical and structural checks, controls tests, route review, training, handover, issue closure.

These controls can share evidence, but they are not interchangeable. A successful factory demonstration cannot confirm destination foundations, final cable routes, local protective devices, weather conditions, barriers, guest clearances, or authority acceptance.

Build a ten-field FAT witness record

FieldWhat to recordExample for a lantern zone
Item and zone IDUnique display, module, circuit, and drawing reference.Dragon gateway, head module, lighting group, current assembly drawing.
Requirement sourceContract clause, approved drawing, finish sample, schedule, or test plan.Approved color sample and released overall dimensions.
Acceptance criterionObservable pass condition and tolerance where appropriate.Modules align, surface is continuous, and the agreed scene operates.
MethodVisual check, measurement, functional test, simulation, or document review.Measure interface points and cycle each control scene.
Witness and responsibilityWho performs, observes, records, and accepts.Supplier quality lead performs; buyer representative witnesses.
ResultActual observation, measurement, or file reference.Measured dimensions, scene video reference, and inspection photographs.
ExceptionClear description, location, extent, and affected requirement.Visible light variation at one seam in the left flower module.
DispositionAccept, accept with actions, retest, or hold.Retest after fabric tension and internal light position are corrected.
Owner and due pointResponsible person and completion deadline or release condition.Supplier finish lead before packing authorization.
Closure evidenceProof that the action was completed and reviewed.Dated close-up and repeat nighttime scene test linked to the issue.
Release rule: Packing should begin only when the agreed release authority can see which items are accepted, conditionally accepted, awaiting retest, or held. A long photo folder without item IDs and dispositions is not an acceptance record.

How do you prepare for a factory acceptance test?

Freeze the test basis

List the controlled documents that govern the review: approved concept and fabrication drawings, dimensions, module strategy, material and finish samples, electrical and controls information, performance expectations, labeling method, packing requirements, and contract deliverables. State their revisions. If one decision is still open, expose it as an assumption or exclusion instead of quietly testing against an obsolete instruction.

Select a representative assembly

Choose the display zones and repeated units that reveal the greatest interface risk. A tall gateway may demonstrate structure, module joints, finish, lighting, and guest clearance. A moving feature may require a separate duty-cycle and guarding review. Repeated flowers can use approved samples and batch evidence, while unique hero pieces may justify full staging.

Issue the procedure before the witness date

The procedure should state prerequisites, sequence, method, instruments, safe access, acceptance criteria, witness points, document pack, exception handling, and release authority. It should also identify which results can be observed remotely and which require physical attendance. This gives both parties time to challenge an incomplete test rather than discovering the gap during the visit.

What should the factory acceptance test checklist cover?

Configuration and dimensions

Confirm the display identity, drawing revision, overall envelope, module breakdown, interface points, bases, anchors or connection provisions, access needs, maintenance approach, and transport constraints. Inspect the assembled silhouette from intended viewing positions, not only from the workshop floor beside it.

Structure, assembly, and finish

Review workmanship visible within the agreed scope, stability of the staged arrangement, module alignment, connection access, sharp-edge control, surface continuity, fabric tension, color consistency, seams, trim, decorative details, and repairability. Destination structural adequacy still depends on the project design basis, support conditions, local professionals, and final installation.

Electrical and control functions

Verify the documented supply and interface basis, circuit identification, accessible connections, internal illumination, agreed scenes, dimming or sequencing behavior, fault response where specified, and the condition of supplied control equipment. Measurements and electrical safety checks should be performed by competent people using the approved procedure.

Environmental and operating features

Inspect exposed connection protection, drainage intent, service access, replaceable parts, moving mechanisms, guarding, noise, and repeated operation where relevant. A factory simulation must state its limitations: rain exposure, wind, ground conditions, ambient temperature, public interaction, and local network integration may only be verifiable at site.

Identification, spares, and documents

Match module IDs to drawings, packing units, installation sequence, cable or controller references, and the packing list. Confirm the agreed manuals, test results, certificates, material records, spare parts, consumables, special tools, repair materials, and training inputs. The lantern procurement evidence guide explains how to connect supplier claims to reviewable records.

Who normally performs and witnesses the FAT?

The manufacturer normally prepares the work, procedure, safe test area, instruments, and records. The buyer or its appointed representative may review the procedure and witness defined points. Depending on the contract and risk, specialist electrical, structural, controls, quality, creative, logistics, or independent inspection personnel may participate. Attendance does not transfer the supplier’s obligations or replace destination professional and authority review.

Use a short opening meeting to confirm the current test basis and a closeout meeting to agree every exception and disposition. Avoid accepting unverified promises such as “we will fix it before shipping” without an owner, due point, release condition, and closure evidence.

Manage exceptions without turning the FAT into a debate

Classify each result using four practical states:

  • Accept: the observed result meets the stated criterion.
  • Accept with actions: a bounded action remains, but the authorized party permits progress under recorded conditions.
  • Retest: the item needs correction and another defined test before release.
  • Hold: the exception affects a critical requirement or creates uncertainty that prevents packing or shipment release.

Do not use severity labels alone. State what work may continue, what is stopped, who decides, and what evidence closes the item. The detailed modular dragon factory test case shows why zone identity and repeatable evidence matter for large assemblies.

Factory acceptance test questions

What is the difference between FAT and SAT?

FAT is conducted at the factory before shipment against the defined pre-shipment scope. SAT is conducted after installation at the destination and can verify real site interfaces, local conditions, integrated operation, and handover. The contract should define both rather than relying on the abbreviations alone.

Must every lantern be fully assembled?

Not necessarily. The answer depends on uniqueness, repetition, interface risk, available space, contract scope, and the evidence strategy. Define which complete zones, samples, modules, and records provide acceptable coverage, and disclose anything that remains unverified until site assembly.

Can photographs replace a witnessed test?

Photos are useful evidence when tied to an item, requirement, date, and result. They may support remote review, but they do not automatically prove function, scale, sequence, measurement, or identity. Agree the remote witness method and file naming before the test.

Does FAT approval release all project risk?

No. FAT addresses the agreed factory scope. Transport, customs, storage, destination handling, local works, installation, site electrical and structural conditions, commissioning, authority requirements, and public operation remain separate controls.

Connect FAT to packing and site acceptance

Once the FAT dispositions permit release, preserve the accepted configuration through photographs, module IDs, protection, packing units, packing lists, handling points, loading order, and custody records. Open issues should travel with the handover register, not disappear when the crates close. The light festival logistics guide helps connect factory release to delivery sequence and site readiness.

At destination, translate the factory record into an installation and site-acceptance plan. Check that the delivered IDs, revisions, closed exceptions, spare parts, assembly instructions, and control scenes match what was released. Our festival lighting projects page sets this test within the broader buyer pathway from concept to delivery and operation.

Preparing a FAT for a custom lantern package? Share the approved display list, drawings, module strategy, finish references, power and control basis, destination conditions, packing boundary, witness needs, and acceptance authority. Contact Zigong Lanterns to discuss a project-specific factory acceptance and evidence plan.

Factory acceptance establishes the controlled configuration before shipment, but the installed display still needs destination verification. This site acceptance test guide for custom lantern displays covers assembly, electrical and control interfaces, visitor routes, punch-list decisions, training, operating release, and handover.

A factory acceptance test is strongest when earlier production controls are traceable. Use this quality inspection checklist for custom lantern manufacturing to define incoming, in-process, pre-close, fit-up, exception, and packing-release records before the formal witness stage.